CERC Denies Start Date Extension of Medium-Term Open Access for a Solar Project
The Commission, however, directed the CTU to revise the bills for the capacity not commissioned
September 12, 2022
The Central Electricity Regulatory Commission (CERC) recently rejected a solar generator’s plea seeking an extension of the start date of medium-term open access (MTOA).
It said that the transmission charges towards MTOA should be billed to the buyer only after the generating station’s commercial operation date.
The Commission added that the bills corresponding to the capacity not commissioned, raised to the Haryana Power Purchase Center (HPPC) by the Central Transmission Utility (CTU), were contrary to the provision of the ‘Sharing Regulations.’ Accordingly, it directed CTU to revise the bills and raise them on the petitioner.
Avaada Energy and Avaada RJHN had filed a petition seeking an extension of the start date of MTOA and restrain the CTU from taking any coercive measures for the non-operationalization of 114.25 MW out of the total 240 MW on the premise that the start date of MTOA was February 1, 2022.
Background
Avaada Energy was declared the successful bidder in a tender floated by HPPC to procure 300 MW of power from solar projects. Later, HPPC issued a letter of intent to purchase 240 MW of solar power from the proposed solar power project.
Avaada Energy applied for Stage I and Stage II connectivity, which CTU granted.
Avaada RJHN, a special purpose vehicle of Avaada Energy, entered into a power purchase agreement (PPA) with HPPC on July 6, 2020, for the supply of 240 MW of solar power.
For evacuation of the power from its project, the petitioner applied for long-term access (LTA) for 240 MW from January 5, 2022, which CTU granted. However, CTU informed Avaada Energy that the LTA would likely be operationalized only on September 25, 2022. Accordingly, Avaada Energy applied for MTOA for evacuation of power, which CTU granted for the period from February 1, 2022, to November 30, 2026.
Since the solar generator achieved the commercial operation of only 125.75 MW by the end of January 2022, it requested CTU for an extension of time for the part operationalization of MTOA for the balance of 114.25 MW up to May 23, 2022.
Avaada Energy submitted that the MTOA of the contracted capacity being 240 MW (out of which 125.75 MW capacity has already been commissioned), had been delayed due to the outbreak of COVID-19 and resultant lockdown, which were considered ‘force majeure’ events.
Commission’s analysis
The Commission observed that Avaada Energy had requested CTU for part operationalization of MTOA upto 125.75 MW from February 1, 2022, and postponement of the balance of 114.25 MW upto May 23, 2022.
The Commission noted that as on February 1, 2022, the part capacity of the petitioner was already operational (125.75 MW) and was covered under the waiver of ISTS charges under the sharing regulations; hence no liability of transmission charges was due for such capacity. However, 114.25 MW was not commercial as on February 1, 2022, for which the petitioner was liable to pay transmission charges.
The state regulator noted that the petitioner had referred to ‘force majeure’ events such as delay of supply from Chinese manufacturers and Covid-19 while requesting an extension of the start date of MTOA. It said that the petitioner had not placed any force majeure notice on record, nor does the MTOA agreement or the connectivity regulations have any provision for force majeure.
It said that the MTOA agreement and the connectivity regulations do not have any provision to defer the start date of LTA or MTOA.
The MTOA agreement as per Regulation 13 of the sharing regulations, provides that transmission charges should be according to CERC norms. Moreover, per the sharing regulations, the petitioner had agreed to share and pay all the applicable transmission charges of the existing transmission system from the commencement of MTOA.
The transmission charges towards MTOA should be billed to the buyer only after the commercial operation date of the generating station. CERC observed that the bills that corresponded to the capacity not commissioned and raised to HPPC by CTU were contrary to the provisions of the sharing regulations. Accordingly, CERC directed CTU to revise the bills and raise the bills on the petitioner per law.
In December 2020, the Haryana Electricity Regulatory Commission had issued an order extending the scheduled commissioning date for a 50 MW open access solar project in the state. It had also approved the PPA for the project meant to help HPPC meet its renewable purchase obligation (RPO) targets.
Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.
Get the most relevant India solar and clean energy news.
RECENT POSTS
LATEST HEADLINES
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules
Mar 24, 2023
Intra-State Sections of Evacuation Infrastructure for Renewables Delayed
Mar 24, 2023
EnBW Takes €2.4 Billion Final Investment Decision on Offshore Wind Project
Mar 24, 2023
India Missed 2022 Renewables Target as Rooftop Solar and Wind fell Short
Mar 24, 2023
Researchers Aim to Accelerate Delivery of Space-Based Solar Power to Earth
Mar 24, 2023
India added an impressive 2.5 GW open access solar capacity in 2022, registering a growth of 92% year-over-year (YoY), according to the 2022 Q4 & Annual Mercom India Solar Open Access Market Report. Karnataka emerged as the to...
March 23, 2023
Markets & Policy
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar ModulesThe Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements betwe...
March 24, 2023
C&I
In Bengaluru, a 100 kW Solar System Can Save C&I Entities ₹1 Million AnnuallyMercom India successfully concluded the C&I Clean Energy Meet 2023 in Bengaluru, where stakeholders in the solar sector and commercial and industrial entities converged to enthusiastically discuss the benefits of renewable ene...
March 24, 2023
Other
Gensol Acquires Solar Tracker Maker Scorpius for ₹1.35 BillionGensol Engineering, a part of solar engineering, procurement, and construction (EPC) company Gensol Group, has acquired India-based solar tracker manufacturer Scorpius Trackers for ₹1.35 billion ($16.4 million). Gensol said the ac...
March 23, 2023
Trending News
Mercom Focus
Researchers Find Solution to Manage Load in Solar PV & Storage Systems
February 28, 2023
February 27, 2023
February 24, 2023
January 17, 2023
Magazine
Latest News
The Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements...
March 24, 2023
The Ministry of New and Renewable Energy (MNRE) told the Parliamentary Standing Committee on Energy that the intra-state stretches of the Green Energy Corridor (GEC) have been delayed due to various reasons, including...
March 24, 2023
German electric utility company Energie Baden-Wuerttemberg (EnBW) has made its final €2.4 billion (~$2.6 billion) investment decision on He Dreiht, a major wind project in the German North Sea. The project has a capacity of 960...
March 24, 2023
The Parliamentary Standing Committee on Energy report has isolated underwhelming progress on rooftop solar and wind energy projects as the primary reason for India falling short of achieving its renewable energy capacity target...
March 24, 2023
Researchers at Northumbria University are studying ways of producing wireless electricity from space to Earth by harvesting the Sun’s energy. U.S.-based aerospace, defense, and information security organization Lockheed Martin...
March 24, 2023
The Maharashtra Electricity Regulatory Commission (MERC) recently directed Hindustan Petroleum Corporation (HPCL) and the Maharashtra State Electricity Distribution Company (MSEDCL) to recompute the delayed payment charge from...
March 24, 2023
The National Renewable Energy Laboratory (NREL) has devised a new way to produce perovskite solar cells that could speed its commercialization. Different layers are typically added sequentially to a conductive glass substrate to...
March 24, 2023
Saudi Arabia-based energy company ACWA Power has signed power purchase and investment agreements with National Electric Grid of Uzbekistan, and the Ministry of Investment, Industry, and Trade to develop new solar and battery...
March 24, 2023
The China Securities Regulatory Commission has approved the registration of CSI Solar, the engineering, procurement, and construction arm of solar module maker Canadian Solar, to issue an initial public offering (IPO). The...
March 24, 2023
Renewable capacity grew by 9.6% in 2022, adding a record 295 GW worldwide. This accounts for 83% of all power capacity added last year and brings the global renewable generation capacity to 3,372 GW by the end of last year, a...
March 24, 2023
Get the most relevant India solar and clean energy news.
POPULAR POSTS
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules
Mar 24, 2023
Intra-State Sections of Evacuation Infrastructure for Renewables Delayed
Mar 24, 2023
EnBW Takes €2.4 Billion Final Investment Decision on Offshore Wind Project
Mar 24, 2023
India Missed 2022 Renewables Target as Rooftop Solar and Wind fell Short
Mar 24, 2023
Researchers Aim to Accelerate Delivery of Space-Based Solar Power to Earth
Mar 24, 2023