Regulator Allows Solar Developer to Recover Interest on Extra Expenditure

The Uttar Pradesh Electricity Regulatory Commission (UPERC) has allowed Adani Solar Energy Chitrakoot One (ASECOL) to recover the carrying cost of the additional...

January 4, 2023

/

Arjun Joshi

/

Solar
thumbnail
Regulator Restrains SECI from Encashing Solar Developer’s Bank Guarantee

The Uttar Pradesh Electricity Regulatory Commission (UPERC) has directed Solar Energy Corporation of India (SECI) to return the performance bank guarantee to ReNew...

December 30, 2022

/

Arjun Joshi

/

Markets & Policy

,

Solar
thumbnail
Uttar Pradesh DISCOM to Tender 10 MW/40 MWh Battery Energy Storage Project

The Uttar Pradesh Electricity Regulatory Commission (UPERC) has approved a request by the Uttar Pradesh Power Corporation (UPPCL) to issue a tender to install five...

September 23, 2022

/

Gourav Mishra

/

Energy Storage

,

Market & Policy
thumbnail
Solar Developer’s Plea for Commissioning Deadline Extension Rejected

The Uttar Pradesh Electricity Regulatory Commission (UPERC) recently rejected a solar developer’s plea seeking an extension of the commissioning deadline on the...

September 9, 2022

/

Rakesh Ranjan

/

Markets & Policy

,

Solar
thumbnail
Captive Power Generator Directed to Purchase RECs to Meet RPO Targets

The Uttar Pradesh Electricity Regulatory Commission (UPERC) recently directed a captive power generator to provide details of the energy that had been procured through...

August 17, 2022

/

Rakesh Ranjan

/

Markets & Policy

,

Solar
thumbnail
Uttar Pradesh Regulator Approves Tariff of ₹2.98/kWh to Procure 125 MW of Solar Power

The Uttar Pradesh Electricity Regulatory Commission (UPERC) recently adopted the tariff of ₹2.98 (~$0.037)/kWh to procure 125 MW of solar power from grid-connected...

July 26, 2022

/

Rakesh Ranjan

/

Markets & Policy

,

Solar
thumbnail
Uttar Pradesh Regulator Adopts Tariff for Procuring Non-Solar Renewable Power

The Uttar Pradesh Electricity Regulatory Commission (UPERC) recently adopted the tariff to procure non-solar renewable power from July 2022 to September 2022. The...

May 26, 2022

/

Rakesh Ranjan

/

Other

,

Renewable Energy
thumbnail
Daily News Wrap-Up: Tata Power Renewables Commissions 300 MW Solar Project in Gujarat

Here are some noteworthy cleantech announcements of the day from around the world: Tata Power Renewables Energy Ltd, a wholly-owned subsidiary of Tata Power, announced...

April 5, 2022

/

Satish Shetty

/

Other

,

Renewable Energy
thumbnail
Uttar Pradesh Regulator Allows Solar Energy Generator to Withdraw Banked Energy

The Uttar Pradesh Electricity Regulatory Commission (UPERC), in a recent petition, heard a solar energy generator’s request to withdraw the banked power. The...

February 21, 2022

/

Rakesh Ranjan

/

Markets & Policy

,

Solar
thumbnail
DISCOM Asked to Pay the Differential Amount for a Bagasse-Based Generation Project

The Uttar Pradesh Electricity Regulatory Commission (UPERC) has directed the state distribution company (DISCOM) to pay the differential amount between November 2017 to...

January 24, 2022

/

Harsh Shukla

/

Other

,

Renewable Energy
thumbnail
Peak & Off-peak Hours Specified for Energy Banking of an Open Access Solar Project

The Uttar Pradesh Electricity Regulatory Commission (UPERC) has ruled that peak hours for banking and withdrawal of energy would be from 18:00 to 24:00 and off-peak...

December 3, 2021

/

Harsh Shukla

/

Markets & Policy

,

Solar
thumbnail
Hindustan Aeronautics Secures Net Metering for a 2.4 MW Rooftop Solar Project

The Uttar Pradesh Electricity Regulatory Commission (UPERC) has approved net metering facility for a 2.4 MW grid-connected rooftop solar project at the Hindustan...

August 30, 2021

/

Harsh Shukla

/

Rooftop

,

Solar
thumbnail
Uttar Pradesh Commission Approves ₹3.29/kWh Tariff for a 150 MW Floating Solar Project

The Uttar Pradesh Electricity Regulatory Commission (UPERC) has approved the tariff of ₹3.29 (~$0.044)/kWh based on a petition filed by the Solar Energy Corporation of...

August 3, 2021

/

Rahul Nair

/

Markets & Policy

,

Solar
thumbnail
Uttar Pradesh Commission Rejects Part Commissioning of a 10 MW Open Access Solar Project

The Uttar Pradesh Electricity Regulatory Commission (UPERC), in a recent order, ruled that AMPSolar Evolution would not be allowed the part commissioning of its two new...

July 23, 2021

/

Rakesh Ranjan

/

Markets & Policy

,

Solar
thumbnail
Uttar Pradesh DISCOM to Pay ₹14.59 Billion for Unmet Renewable Purchase Obligation

The Uttar Pradesh Electricity Regulatory Commission (UPERC), in a recent order, directed Uttar Pradesh Power Corporation Limited (UPPCL) to deposit ₹72.45 billion (~$978...