SECI Asked to Compensate Maharashtra DISCOM for Delay in Commissioning Solar Projects

The Commission directed SECI to reimburse the money accrued due to reduction in tariff

thumbnail

The Maharashtra Electricity Regulatory Commission (MERC) has asked the Solar Energy Corporation of India (SECI) to compensate the Maharashtra State Electricity Distribution Company Limited (MSEDCL) for the short supply of energy due to which it had look to other sources to fulfill its renewable purchase obligation (RPO).

It directed SECI to return the money if the bank guarantee was encashed after creating the payment security mechanism. It also asked SECI to reimburse the money accrued following the tariff reduction due to delay in commissioning of the projects.

MSEDCL had filed a petition with the Commission seeking compensation as per the power sale agreement (PSA) executed with SECI and compensation on account of the delay in the project’s commercial operation date (COD) as per the power purchase agreements (PPA) with the project developers.

Background

SECI carried out two separate bids for selecting solar power developers for 500 MW projects in each case to be set up in Maharashtra for sale to MSEDCL based on the Request for Selection (RfS) dated August 27, 2015, and February 24, 2016.

SECI and MSEDCL entered into two PSAs on November 04, 2016, and December 01, 2016, with SECI having to sell solar power to MSEDCL by buying the same from the selected developers.

The commissioning dates for Batch-III projects was May 10, 2017, for the open content category (450 MW) and August 16, 2017, for the domestic content requirement (DCR) category (50 MW).  The commissioning date for 500 MW Batch-IV projects was December 23, 2017.

The agreed capacity of power to be sold by SECI to MSEDCL under both the PSAs was 500 MW each, respectively.

SECI started supplying power to MSEDCL from June 2017 in a phased manner. However, some of the projects that SECI had tied up for were delayed, leading to a shortfall in supply of power as agreed under the PSA executed between MSEDCL and SECI.   

In its submission, SECI said that it was acting only as an intermediary nodal agency to facilitate such purchase and resale of electricity.

The delay in commissioning and commercial operation of the developers’ solar projects led to a delay in commencement of supply of power for reasons not attributable to SECI.

It said that there was no avenue available for MSEDCL to seek a reduction in the applicable tariff of ₹4.50 (~$0.061)/kWh.

SECI argued that the amount related to the liquidated damages and reduction in tariff provided for in the PPAs was not required to be remitted to MSEDCL. There was no monetary remedy provided under the PSAs for the delay in commissioning of the projects.

Commission’s Analysis

After going through all the facts, the Commission said that the PSA and PPA provisions established that compensation for the short supply of energy in any contract year was recoverable by SECI from the developer for remitting it to MSEDCL.

However, such compensation for the short supply of energy was relevant only for the period after the project’s COD. SECI, in its submission, had also agreed with the same.

Accordingly, the Commission said, MSEDCL may revise its claim for the short supply of energy by considering only the period post the COD of the projects.

The Commission observed that to make timely payments to the developers, the National Solar Mission (NSM) guidelines had specified the development of a ‘Payment Security Fund.’

“Accordingly, money received from encashment of bank guarantee has to be deposited into the above-stated fund. Hence, MSEDCL cannot claim such an amount from SECI. However, MNRE has specified a ceiling limit of such fund, i.e., three months of payments to the projects set up under the guidelines. Once the limit is reached, the benefit of any subsequent encashment of the bank guarantee would need to be passed on to MSEDCL. To enable MSEDCL to claim such benefit, SECI is directed to provide details of the fund created, its ceiling level considering three months payment to the project, and details of the bank guarantee enchased. Based on such details, if applicable, MSEDCL may claim amount received by SECI towards encashment of the bank guarantee,” the Commission noted.

The state regulator added that the tariff for the sale of energy to MSEDCL was linked to tariff discovered for individual projects through reverse auction process plus SECI’s trading margin of ₹0.07 (~$0.0009)/kWh. It was also important to note that the PSA had put higher limits, i.e., ₹4.50 (~₹0.061)/kWh, which can be levied on MSEDCL.

Therefore, when there is a reduction in tariff on delay in commissioning the project, SECI will have to pass on the same to MSEDCL.

From the detailed project commissioning status submitted by SECI, the Commission stated that several projects had been commissioned with a delay of more than three months. All such projects must have been subjected to the reduced tariff as per the PPA provisions, and SECI must have accrued the benefit of the reduced tariff.

Therefore, the Commission directed SECI to pass on any benefit accrued to it based on a reduction in the tariff to MSEDCL within a month.

In September last year, MERC asserted that it was the appropriate Commission to adjudicate a dispute between SECI and MSEDCL. The MSEDCL had filed a petition with the Commission seeking compensation from SECI following a shortfall in the supply of power as agreed upon under the PSA between both the parties.

Earlier, Arina Solar had filed a petition with the Central Electricity Regulatory Commission (CERC) requesting it to direct SECI to return its performance bank guarantee of ₹500 million (~$6.67 million).

 Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.

RELATED POSTS

thumbnail
Top 5 States for Open Access Solar Installations in CY 2022

India added an impressive 2.5 GW open access solar capacity in 2022, registering a growth of 92% year-over-year (YoY), according to the 2022 Q4 & Annual Mercom India Solar Open Access Market Report. Karnataka emerged as the to...

March 23, 2023

Markets & Policy

Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules

The Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements betwe...

March 24, 2023

C&I

In Bengaluru, a 100 kW Solar System Can Save C&I Entities ₹1 Million Annually

Mercom India successfully concluded the C&I Clean Energy Meet 2023 in Bengaluru, where stakeholders in the solar sector and commercial and industrial entities converged to enthusiastically discuss the benefits of renewable ene...

March 24, 2023

Other

Gensol Acquires Solar Tracker Maker Scorpius for ₹1.35 Billion

Gensol Engineering, a part of solar engineering, procurement, and construction (EPC) company Gensol Group, has acquired India-based solar tracker manufacturer Scorpius Trackers for ₹1.35 billion ($16.4 million). Gensol said the ac...

March 23, 2023

Magazine

DON'T MISS AN ISSUE!

Mercom Cleantech Magazine

Get Your Copy Today!

magazines

Latest News

thumbnail
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules

The Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements...

March 24, 2023

thumbnail
Intra-State Sections of Evacuation Infrastructure for Renewables Delayed

The Ministry of New and Renewable Energy (MNRE) told the Parliamentary Standing Committee on Energy that the intra-state stretches of the Green Energy Corridor (GEC) have been delayed due to various reasons, including...

March 24, 2023

thumbnail
EnBW Takes €2.4 Billion Final Investment Decision on Offshore Wind Project

German electric utility company Energie Baden-Wuerttemberg (EnBW) has made its final €2.4 billion (~$2.6 billion) investment decision on He Dreiht, a major wind project in the German North Sea. The project has a capacity of 960...

March 24, 2023

thumbnail
India Missed 2022 Renewables Target as Rooftop Solar and Wind fell Short

The Parliamentary Standing Committee on Energy report has isolated underwhelming progress on rooftop solar and wind energy projects as the primary reason for India falling short of achieving its renewable energy capacity target...

March 24, 2023

thumbnail
Researchers Aim to Accelerate Delivery of Space-Based Solar Power to Earth

Researchers at Northumbria University are studying ways of producing wireless electricity from space to Earth by harvesting the Sun’s energy. U.S.-based aerospace, defense, and information security organization Lockheed Martin...

March 24, 2023

thumbnail
Regulator Directs Wind Energy Firm, MSEDCL, to Recompute Delayed Payment Charge

The Maharashtra Electricity Regulatory Commission (MERC) recently directed Hindustan Petroleum Corporation (HPCL) and the Maharashtra State Electricity Distribution Company (MSEDCL) to recompute the delayed payment charge from...

March 24, 2023

thumbnail
One-Step Coating Could Make Perovskite Solar Cells Commercially Viable

The National Renewable Energy Laboratory (NREL) has devised a new way to produce perovskite solar cells that could speed its commercialization. Different layers are typically added sequentially to a conductive glass substrate to...

March 24, 2023

thumbnail
ACWA Power to Develop Solar and Energy Storage Projects in Uzbekistan

Saudi Arabia-based energy company ACWA Power has signed power purchase and investment agreements with  National Electric Grid of Uzbekistan, and the Ministry of Investment, Industry, and Trade to develop new solar and battery...

March 24, 2023

thumbnail
China Securities Regulatory Commission Approves Canadian Solar’s IPO

The China Securities Regulatory Commission has approved the registration of CSI Solar, the engineering, procurement, and construction arm of solar module maker Canadian Solar, to issue an initial public offering (IPO). The...

March 24, 2023

thumbnail
Renewables Accounted for 83% of the Total Generation Capacity Added in 2022

Renewable capacity grew by 9.6% in 2022, adding a record 295 GW worldwide. This accounts for 83% of all power capacity added last year and brings the global renewable generation capacity to 3,372 GW by the end of last year, a...

March 24, 2023

MORE NEWS