MERC Allows Time Extension for Solar Projects Facing Transmission Delays
Transmission infrastructure for some projects is delayed by up to 18 months
October 5, 2026
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Maharashtra Electricity Regulatory Commission (MERC) has allowed, in principle, a petition seeking revision of the scheduled commencement of supply dates (SCSD) for solar projects where the associated transmission evacuation infrastructure is expected to be commissioned after the contractual timelines.