Karnataka Commission Allows Tariff of ₹7.08/kWh for a 10 kW Rooftop Solar Project

The Commission directed BESCOM to release payments to the tune of ₹269.45 million to the petitioner

February 1, 2022

thumbnail

The Karnataka Electricity Regulatory Commission (KERC), in a recent order, ruled in favor of a rooftop solar installer and said that the installer had commissioned the project well before the time set by the Bangalore Electricity Supply Company (BESCOM) and was entitled to a tariff of ₹7.08 (~$0.094)/kWh as per the provisions of the power purchase agreement (PPA).

The Commission also said that BESCOM should calculate the amount withheld from the developer from January 2018 to March 2021 as per the tariff agreed in the PPA within two months.

L Laksmipathy had filed a petition with the Commission seeking directions for BESCOM to release ₹269,458 (~$3,584) as per the tariff agreed under the PPA for the period from January 2018 to March 2021. It had also requested the Commission to direct BESCOM to pay an amount of ₹59,931 (~$797.33) as interest at 1% on the total outstanding amount.

Background

The petitioner had installed a 10 kW rooftop solar system at his residence and submitted the work completion report within six months from the date of the approval of the PPA, i.e., from July 28, 2017, until January 22, 2018.

The petitioner claimed that BESCOM was required to make payments at the agreed tariff of ₹7.08 (~$0.094)/kWh within 30 days of raising the monthly electricity bill. However, BESCOM failed to discharge its obligations as per terms of the PPA.

The petitioner argued that the project was completed well before the scheduled date of January 27, 2018, and there was no delay in the installation and commissioning of the project. Also, the tariffs could only be altered if there was a delay in the commissioning of the project.

BESCOM, in its submission, said that the petitioner had misinterpreted the facts and had failed to commission the project on time. The petitioner was required to commission the project on or before 180 days, i.e., January 24, 2018, as per the KERC Regulations.

BESCOM further added that as the petitioner had not complied with the obligation to complete the project by January 24, 2018, and was bound to execute the supplementary PPA and accept the lower tariff.

Commission’s analysis

The Commission observed that the project was installed within the prescribed time as per the provisions of the PPA. Per the PPA, the consumer should have commissioned the rooftop solar project within six months from the date of approval of the PPA, which he did as the project was commissioned on January 27, 2018.

The state regulator noted that the petitioner was entitled to an amount of ₹269,458 as per the tariff agreed under the PPA. Also, the petitioner was entitled to interest on the outstanding amount.

KERC added that the petitioner and BESCOM were not required to sign SPPA, as the project was commissioned within the scheduled date.

Last July, the Appellate Tribunal for Electricity (APTEL) directed KERC to review its earlier order regarding the tariff reduction for the delayed rooftop projects and pass the order within three months.

Earlier, KERC had issued an order in favor of BESCOM and asked Applied Solar Technologies to revise its rooftop solar tariff to ₹5.20 (~$0.07)/kWh from the ₹9.56 (~$0.13) tariff it claimed.

Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.

RELATED POSTS