Bondada Engineering Commissions 120 MW of Solar Projects

The projects are located in Maharashtra and Tamil Nadu

January 6, 2026

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


Bondada Engineering, a Hyderabad-based engineering, procurement, and construction (EPC) company, commissioned 120.46 MW of solar projects in December 2025 for Paradigm IT, Maharashtra State Power Generation Company, and NLC India.

The projects are located in the Dhule, Amravati, Hingoli, Pathardi, Shevgaon, Kannad, and Dharni districts of Maharashtra, as well as in Neyveli, Tamil Nadu.

The company is also an independent power producer (IPP) having a presence in wind, hybrid, and storage projects, including solar with battery energy storage systems (BESS) and standalone BESS systems. The company also offers operation and maintenance services.

The company was one among three winners in Tamil Nadu Green Energy Corporation’s auction to set up 500 MW/1,000 MWh standalone BESS projects in six locations in Tamil Nadu on a build-own-operate basis. Bondada Engineering won 200 MW/400 MWh at a tariff of ₹246,000 (~$2,856.81)/MW/month to set up one BESS project each at Vellalaviduthi and Thennampatty substations. Under the viability gap funding (VGF) support from the Ministry of Power, the projects will receive VGF of 30% of the capital cost for the BESS or ₹2.7 million (~$31,101)/MWh, whichever is lower. This funding will be disbursed in five tranches.

In November 2025, the company won a 225 MW/450 MWh standalone BESS project in Transmission Corporation of Andhra Pradesh’s (APTRANSCO) auction to develop 1,000 MW/2,000 MWh standalone BESS projects in the state at a tariff of ₹164,000 (~$1,833)/MW/month.

Recently, the company was among the few to win orders from NTPC Renewable Energy for balance-of-system (BoS) works for 1.4 GW of grid-connected solar power projects in Chitrakoot (2 x 400 MW) and Lalitpur (2 x 300 MW) in Uttar Pradesh.  Bondada won the order for 300 MW of solar projects in Lalitpur-1, valued at ₹3.91 billion (~$43.52 million).

Earlier, Bondada Engineering had secured an EPC order from NLC India Renewables for BoS works for setting up 810 MW solar projects at the Rajasthan Rajya Vidyut Utpadan Nigam’s solar park in Bikaner, Rajasthan. The order consisted of separate BoS works for 400 MW and 410 MW. The contract’s estimated cost is ₹9.45 billion (~$105.47 million).

Also, last year, the company received a letter of intent from the Adani Group to supply BoS equipment for a 650 MW solar project at the Khavda Renewable Energy Park, Gujarat.

Subscribe to Mercom’s Solar Project Tracker for a comprehensive database of large-scale solar projects covering commissioned and under-development projects from the beginning of the National Solar Mission.