Solar Leads 248 GW Renewable and Storage Transmission Connectivity Pipeline

In 2026 and 2027, connectivity for 133 GW of renewables and storage is likely to become effective

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


Nearly 248 GW of power grid connectivity and General Network Access (GNA) granted to renewable energy and storage projects is expected to become effective between August 2026 and 2031. Around 53.4 GW of renewable, storage, and hydro connectivity is expected to become effective in 2026, followed by nearly 80 GW in 2027.