SECI Tenders 2 GW of ISTS-Connected Wind Projects Under Tranche-V

The time-frame for the commissioning has been set at 18 months from the effective date of the PPA

May 29, 2018

thumbnail

After the success of the recently held wind auctions, the Solar Energy Corporation of India (SECI) has now tendered 2 GW of Inter-State Transmission System (ISTS)-connected wind power projects to be developed across the country under Tranche-V.

The bid-submission deadline is July 10, 2018.

The projects will be developed on build own operate (BOO) basis. The successful bidders will enter into Power Purchase Agreements (PPAs) with SECI for a period of 25 years. A single bidder can bid for a minimum 50 MW and maximum of 300 MW capacity.

The scope of work includes the setting up of the wind power projects as well as the transmission network up to the delivery point.

All approvals, permits, and clearances required for the development and connectivity – including those required by state governments – have been made the responsibility of the project developer. The maintenance of the transmission system up to the interconnection point will also be the responsibility of the developer. This is a global tender but Limited Liability Partnerships (LLPs) are not eligible for participation.

The project developer must report tie-up of 100 percent of the financing arrangements for the project within seven months from the effective date of the PPA.

During the course of the PPA, if it is found that the developer has not been able to generate minimum energy in any given year corresponding to the lower limit of the Capacity Utilization Factor (CUF) declared, the developer will pay the compensation provided in the PPA, as payable to SECI. The SECI can write off the penalty in case of grid non-availability for evacuation, which is beyond the control of the developer.

In case the availability is more than the maximum CUF specified, the generator can sell it to any other entity only if SECI refuses to procure. In case SECI purchases the excess generation over and above 10 percent of the declared annual CUF, the same will be done at 75 percent of the PPA tariff.

The time-frame for the commissioning of the project has been set at 18 months from the effective date of the PPA. For delay up to six months, PBG on per day basis proportionate to capacity not commissioned will be deducted. If project commissioning is delayed beyond six months, the tariff quoted will be reduced by 0.50 paise/kWh per day for the remaining capacity. A developer will be allowed a maximum of 27 months to commission the project.

SECI’s latest tender comes at a time when wind tariffs have been gradually declining. In the recently concluded SECI wind auction for 2 GW, the lowest (L1) tariff quoted by the bidders stood at ₹2.51 (~$0.0386)/kWh. The capacity was tendered by SECI in February 2018.

Image credit: Flickr

RELATED POSTS