ReNew Power Fined for Project Commissioning Delay but PPA Not Terminated

The Supreme Court has asked ReNew Power to pay ₹119 million for delay in project commissioning

thumbnail

The Supreme Court of India has asked renewable energy project developer ReNew Power to pay a penalty of ₹119 million (~$1,827,700) to the Madhya Pradesh Power Management Company Limited (MPPMCL) for delaying the commissioning of a solar project in the state by more than 210 days.

The Supreme Court was responding to an appeal put forth by MPPMCL to provide relief in the matter of a 51 MW grid-connected solar photovoltaic (PV) project being developed by ReNew Power for which MPPMCL had entered into a 25-year Power Purchase Agreement (PPA) with the company.

The apex court, however, has set aside the cancellation of the PPA which was initiated by MPPMCL.

An official working with MPPMCL told Mercom, “The Honorable Supreme Court’s order is paramount, we will get the Performance Bank Guarantee (PBG) amount, the PPA will not be terminated.”

When asked why the Jabalpur High Court order was not accepted, though it was the same as the SC order, the MPPMCL official said, “MPPMCL felt we were the aggrieved party and were not satisfied with Jabalpur High Court’s order, hence we appealed.”

“The Supreme Court judgement in the case of ReNew Power is a shot in the arm for the renewable sector. The Supreme Court has passed a landmark judgement wherein it has upheld the order of the Madhya Pradesh High Court in favor of ReNew Power, which labelled the termination of the contract by MPPMCL as unlawful and arbitrary”, said Pranav Mehta, the founder and chairman of National Solar Energy Federation of India (NSEFI), in an emailed response.

Mehta further added, “The judgement has come as a shot in the arm for the renewable sector as it is an investment intensive sector and the Independent Power Producers (IPPs) put in substantial capital investment upfront – to the tune of $1 million per MW of installed capacity. The Central Electricity Authority estimates that the sector needs $100 billion of investment in the next five years if India has to achieve its target of 175 GW of renewables by 2022. In this backdrop, it is imperative that the sanctity of the PPAs signed with various IPPs is maintained else it will dampen the image of India as a preferred investment destination for renewables.”

Quick Recap of the Case

ReNew Power had won the contract to develop a 51 MW grid-connected solar PV project by participating in a 300 MW solar tender issued by MPPMCL. ReNew had quoted a tariff of ₹5.457 (~$0.0839)/kWh and was issued a Letter of Intent (LoI) on October 23, 2015. The PPA was signed between MPPMCL and ReNew on November 10, 2015.

According to the tender document, the developer needed to procure land to develop the solar project. The state government had allotted approximately 103 acres for the project but the project work could not commence due to encroachment issues.

On December 29, 2016, the MPPMCL issued a letter stating, “Change in the location of land may be permitted after 210 days of signing of PPA by MPPMCL, subject to provision 2.5 and 2.6 of said PPA.”

On March 22, 2017, ReNew informed the MPPMCL that it had acquired 253 acres of land for the project. On August 11, 2017, in line with provision 2.5, MPPMCL terminated the PPA and ordered encashment of the contract PBG, citing a delay of 16 days beyond the nine-month extension.

Later, ReNew Power approached the Jabalpur High Court to provide relief in the matter. The Jabalpur High Court ruled that the encashed PBG need not be returned, but it also put aside the termination of PPA.

The MPPMCL then approached the Supreme Court in October 2017. The Supreme Court put a stay on the Jabalpur High Court’s order and asked MPPMCL to return the encashed PBG.

The new judgement by the Supreme Court will provide some relief to ReNew Power and to the general sentiment of project developers in the country. Penalizing for a delay is within the sanctity of the contract entered by both parties but rescinding a PPA of a project nearing completion is taking a step backward.

“Developers already feel PPAs are one sided and any delays on the part of government agencies has no consequence and cannot be questioned. Meanwhile, delays even due to legitimate reasons beyond control (mostly land issues) on the part of developers is quickly punished through fines and encashment of bank guarantees. Hopefully this case sets a precedence that legitimate reasons on both sides need to be considered and treated fairly.” said Raj Prabhu, CEO of Mercom Capital Group.

RELATED POSTS

thumbnail
Top 5 States for Open Access Solar Installations in CY 2022

India added an impressive 2.5 GW open access solar capacity in 2022, registering a growth of 92% year-over-year (YoY), according to the 2022 Q4 & Annual Mercom India Solar Open Access Market Report. Karnataka emerged as the to...

March 23, 2023

Markets & Policy

Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules

The Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements betwe...

March 24, 2023

C&I

In Bengaluru, a 100 kW Solar System Can Save C&I Entities ₹1 Million Annually

Mercom India successfully concluded the C&I Clean Energy Meet 2023 in Bengaluru, where stakeholders in the solar sector and commercial and industrial entities converged to enthusiastically discuss the benefits of renewable ene...

March 24, 2023

Other

Gensol Acquires Solar Tracker Maker Scorpius for ₹1.35 Billion

Gensol Engineering, a part of solar engineering, procurement, and construction (EPC) company Gensol Group, has acquired India-based solar tracker manufacturer Scorpius Trackers for ₹1.35 billion ($16.4 million). Gensol said the ac...

March 23, 2023

Magazine

DON'T MISS AN ISSUE!

Mercom Cleantech Magazine

Get Your Copy Today!

magazines

Latest News

thumbnail
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules

The Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements...

March 24, 2023

thumbnail
Intra-State Sections of Evacuation Infrastructure for Renewables Delayed

The Ministry of New and Renewable Energy (MNRE) told the Parliamentary Standing Committee on Energy that the intra-state stretches of the Green Energy Corridor (GEC) have been delayed due to various reasons, including...

March 24, 2023

thumbnail
EnBW Takes €2.4 Billion Final Investment Decision on Offshore Wind Project

German electric utility company Energie Baden-Wuerttemberg (EnBW) has made its final €2.4 billion (~$2.6 billion) investment decision on He Dreiht, a major wind project in the German North Sea. The project has a capacity of 960...

March 24, 2023

thumbnail
India Missed 2022 Renewables Target as Rooftop Solar and Wind fell Short

The Parliamentary Standing Committee on Energy report has isolated underwhelming progress on rooftop solar and wind energy projects as the primary reason for India falling short of achieving its renewable energy capacity target...

March 24, 2023

thumbnail
Researchers Aim to Accelerate Delivery of Space-Based Solar Power to Earth

Researchers at Northumbria University are studying ways of producing wireless electricity from space to Earth by harvesting the Sun’s energy. U.S.-based aerospace, defense, and information security organization Lockheed Martin...

March 24, 2023

thumbnail
Regulator Directs Wind Energy Firm, MSEDCL, to Recompute Delayed Payment Charge

The Maharashtra Electricity Regulatory Commission (MERC) recently directed Hindustan Petroleum Corporation (HPCL) and the Maharashtra State Electricity Distribution Company (MSEDCL) to recompute the delayed payment charge from...

March 24, 2023

thumbnail
One-Step Coating Could Make Perovskite Solar Cells Commercially Viable

The National Renewable Energy Laboratory (NREL) has devised a new way to produce perovskite solar cells that could speed its commercialization. Different layers are typically added sequentially to a conductive glass substrate to...

March 24, 2023

thumbnail
ACWA Power to Develop Solar and Energy Storage Projects in Uzbekistan

Saudi Arabia-based energy company ACWA Power has signed power purchase and investment agreements with  National Electric Grid of Uzbekistan, and the Ministry of Investment, Industry, and Trade to develop new solar and battery...

March 24, 2023

thumbnail
China Securities Regulatory Commission Approves Canadian Solar’s IPO

The China Securities Regulatory Commission has approved the registration of CSI Solar, the engineering, procurement, and construction arm of solar module maker Canadian Solar, to issue an initial public offering (IPO). The...

March 24, 2023

thumbnail
Renewables Accounted for 83% of the Total Generation Capacity Added in 2022

Renewable capacity grew by 9.6% in 2022, adding a record 295 GW worldwide. This accounts for 83% of all power capacity added last year and brings the global renewable generation capacity to 3,372 GW by the end of last year, a...

March 24, 2023

MORE NEWS