Regulator Restrains DISCOM from Coercive Action Against a Solar Developer
Avaada and Maharashtra DISCOM are locked in a dispute over the project timeline
January 12, 2023
The Maharashtra Electricity Regulatory Commission (MERC) has directed the Maharashtra State Electricity Distribution Company (MSEDCL) to refrain from taking any coercive action against a solar power generator until the dispute on financial closure and scheduled commercial operation date is resolved.
The order was passed in response to an interlocutory application filed by Avaada MH Sustainable seeking an extension of the scheduled commercial operation date for a 250 MW solar power project.
Background
In the original petition filed by Avaada MH Sustainable, it had requested an extension citing certain force majeure events.
The solar power generator said that it has completed 200 MW of the project capacity and is in the advanced stage of commissioning the balance 50 MW.
The petitioner cited the following reasons for the delay:
- Delay by MSEDCL in the execution of the power purchase agreement (PPA) after the Commission had asked MSEDCL to do so within two weeks from February 16, 2021
- Delay by the Maharashtra State Electricity Transmission Company (MSETCL) in granting connectivity to the project
- Delay by MSETCL in approving the design and program for transmission infrastructure
- Delay on account of the COVID-19 pandemic
- Delay on account of torrential rainfall at the project site, which resulted in a flood-like situation
Avaada, in its submission, stated that MSEDCL had unilaterally amended the provision of PPA related to the timeline for the financial closure from 18 months to 12 months, which may lead to a penalty for any delay.
It added that the financial closure was required to be achieved by January 17, 2022, which even without the extension on account of COVID-19 was achieved on December 27, 2021.
MSEDCL clarified that on account of a typographical error in the PPA dated August 10, 2021, concerning the financial closure date (18 months instead of 12 months) cannot be taken into account.
Commission’s analysis
The Commission noted that as per the submission of the petitioner, it has strong apprehension that MSEDCL might levy liquidated damages on the applicant or may encash the performance bank guarantee (PBG).
The Commission observed that the main dispute was regarding the dates of financial closure and scheduled commercial operation date as specified in the PPA and the request for selection (RfS).
The provisions of the PPA state that the project should be commissioned within 15 months for projects being set up in the solar park, and within 18 months for projects being set up outside the solar park from the effective date of the PPA on July 17, 2020.
The Commission added that MSEDCL’s argument of a typographical error in writing the dates for financial closure needed to be decided on its merit after hearing all the parties in the main matter.
MERC said that the solar power generator had already achieved financial closure on December 27, 2021, which was not disputed by MSEDCL.
The Commission added that as per the provisions of PPA, if the extension of the scheduled operation date is allowed by them in the main matter, the penalty amount will be required to be returned to the petitioner within 30 days of the achievement of the commissioning date.
Therefore, there was no need to impose such a penalty when the dispute on the date of financial closure and scheduled commercial operation date was yet to be decided in the main matter.
In August last year, MERC extended the scheduled commercial operation date of Avaada Sunce Energy’s (Avaada) 350 MW solar project by 59 days. The extension was granted because of certain force majeure events, including COVID-19 and disruption in the import of modules from China, impacting the project’s progress.
Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.
Get the most relevant India solar and clean energy news.
RECENT POSTS
LATEST HEADLINES
Maharashtra Approves Tariffs for 8.7 MW of Solar Power Under KUSUM Program
Mar 21, 2023
Brookfield to Aquire KKR’s 50% Stake in Renewable Developer X-Elio
Mar 21, 2023
NTPC’s Subsidiary Will Develop Renewable Projects for IndianOil Refineries
Mar 21, 2023
Constant Climate-Centric Funding Can Limit Global Temperature Under 1.5°C
Mar 21, 2023
India Voices Concern over Europe’s Carbon Tariff Measure at WTO
Mar 21, 2023
India added 2.5 GW of solar open access in the calendar year (CY) 2022, a year-over-year (YoY) increase of 92% from the 1.3 GW installed in CY 2021, according to the newly released 2022 Q4 & Annual Mercom India Solar Open Acce...
March 15, 2023
Solar
Kerala Issues Empanelment Tender for 100 MW of Solar ProjectsThe Kerala State Electricity Board (KSEB) has invited bids to empanel solar developers to set up 100 MW of grid-connected rooftop and ground-mounted projects. Empanelled vendors also must furnish operation and maintenance (O&M...
March 20, 2023
Tenders and Auctions
Gujarat Invites Bids to Procure 500 MW of Wind Power with Greenshoe OptionGujarat Urja Vikas Nigam (GUVNL) has invited bids to procure power from 500 MW of grid-connected wind projects (Phase V) with a greenshoe option of an additional capacity of up to 500 MW. The last day to submit the bids online is ...
March 17, 2023
Rooftop
MSMEs Adopt Solar Readily If Savings on Power Bills Cover EMI Cost: InterviewSmall businesses are open to adopting rooftop solar if loan repayment is not an additional burden and is equal to their savings on electricity bills. Entities in the commercial and industrial (C&I) segment are increasingly mov...
March 17, 2023
Trending News
Tender & Auctions
Indian Oil Floats O&M Tender for 8 MW Solar Project in Ahmedabad
March 14, 2023
Technology
Researchers Find Solution to Manage Load in Solar PV & Storage Systems
February 28, 2023
February 27, 2023
February 24, 2023
January 17, 2023
Magazine
Grid
Sterlite Bags ISTS Project to Evacuate 20 GW of Renewables in Rajasthan
March 13, 2023
Latest News
The Maharashtra Electricity Regulatory Commission (MERC) has adopted tariffs of ₹3.28 (~$0.039)/kWh, ₹3.29 (~$0.039)/kWh, and ₹3.30 (~$0.040)/kWh for the procurement of 8.7 MW of solar power on a long-term basis. The Commission...
March 21, 2023
Global investment firm Kohlberg Kravis Roberts (KKR) has agreed to sell 50% of its stake in renewable developer X-ELIO to its joint venture partner Brookfield Renewable. Financial details were not disclosed. Since KKR’s...
March 21, 2023
NTPC Limited’s wholly owned subsidiary, NGEL, has entered into a joint venture agreement with Indian Oil Corporation (IOCL) to develop renewable energy projects that can meet round-the-clock power requirements to meet the...
March 21, 2023
Financial support from developed economies to developing nations which is a critical enabler of climate action has been inadequate, said scientists in the latest Intergovernmental Panel on Climate Change (IPCC) report...
March 21, 2023
India has expressed concern about the carbon border measures proposed by the European Union (EU) at a recent meeting of the World Trade Organization’s (WTO) Committee on Trade and Environment. Presenting a paper on the increasing...
March 21, 2023
JSW Neo Energy (JSW Energy) and Greenko KA 01 IREP (Greenko) have won the Power Company of Karnataka’s (PCKL) auction to supply 1 GW of energy for 8 hours daily from pumped hydro storage projects providing continuous 5-hour...
March 21, 2023
Sterling and Wilson Renewable Energy, the solar engineering, procurement, and construction (EPC) arm of Shapoorji Pallonji Group, won NTPC’s tender for the balance of system (BOS) package to develop 1.2 GW (4*300 MW) of solar...
March 21, 2023
Indian Oil Corporation (IOCL) has invited bids for the operation and maintenance (O&M) of an existing 8 MW solar power project at the LPG bottling plant at Sanand in Ahmedabad for five years. The last date to submit the bids...
March 21, 2023
Researchers at the Indian Institute of Technology Mandi (IIT Mandi) have claimed a breakthrough in producing metal oxide layers for use in advanced architecture silicon solar cells using a cost-effective method. This innovative...
March 21, 2023
The government has allowed NTPC to invest in its subsidiary, NTPC Green Energy (NGEL), beyond the limit allowed for a ‘maharatna’ central public sector enterprise (CPSE). The extant guidelines prescribe a ceiling of 30% of a...
March 21, 2023
Get the most relevant India solar and clean energy news.
POPULAR POSTS
Maharashtra Approves Tariffs for 8.7 MW of Solar Power Under KUSUM Program
Mar 21, 2023
Brookfield to Aquire KKR’s 50% Stake in Renewable Developer X-Elio
Mar 21, 2023
NTPC’s Subsidiary Will Develop Renewable Projects for IndianOil Refineries
Mar 21, 2023
Constant Climate-Centric Funding Can Limit Global Temperature Under 1.5°C
Mar 21, 2023
India Voices Concern over Europe’s Carbon Tariff Measure at WTO
Mar 21, 2023
JSW and Greenko Win Karnataka’s Bid for 1 GW of Pumped Storage Projects
Mar 21, 2023
Sterling and Wilson Bags BoS Package Tender for 1.2 GW Solar Projects
Mar 21, 2023