Karnataka Court Quashes KERC Order Increasing Wheeling Charges for Open Access Power

KERC not authorized to determine power tariff time to time says the court

thumbnail

The Karnataka High Court has quashed an order issued by the Karnataka Electricity Regulatory Commission (KERC) relating to an increase in wheeling charges for open access power consumers in the state. The Karnataka High Court order has brought relief to all renewable energy generators trading power through open access in Karnataka.

The court, in its order, has reiterated the principle of settled contracts which lends certainty to power purchase agreements (PPAs) and imposes confidence in investors.

Case History

In May 2018, KERC had issued an order setting the wheeling, transmission charges to be levied on renewable energy projects in the state. The order has been in effect since April 1, 2018, and will be in effect till March 31, 2020.

According to the KERC, all renewable projects (other than the captive projects availing the benefit of the renewable energy certificate mechanism) which have not completed ten years of commercial operation as on March 31, 2018, had to pay 25 percent of the normal transmission or wheeling charges fixed by the CERC, in cash.

The KERC, in its order, had also stated that these renewable energy projects would be liable to bear the losses incurred in the applicable line, as approved by the KERC, by deductions from the net injected energy. It had also directed the renewable energy projects to pay two percent in banking charges.

This was a five-fold increase in wheeling charges for open access consumers in the state of Karnataka. In response, a few renewable energy project developers operating in Karnataka filed writ petitions in the Karnataka High Court challenging this order.

Towards the end of May 2018, the vacation bench of the Karnataka High Court imposed an indefinite stay on the KERC order.

Renewable energy developers had petitioned on the grounds that the KERC does not have the power to suo motu review its own tariff orders and that the KERC broke a specific and unequivocal promise. The Karnataka High Court upheld both the points of reasoning put forth by the renewable energy project developers.

When contacted, Shodhan Babu, an official at the Law Offices of Panag and Babu, (the law firm representing petitioners) replied, “The Honorable Karnataka High Court has held that Sections 62 and 64 of the Electricity Act confers the power on the KERC to determine the tariff. However, once settled, and the contracts have been entered based on the tariff orders without any request made by either party to the power purchase agreement (PPA), the KERC is not conferred with the power to determine tariff from time to time.”

Key Findings in Karnataka High Court’s Order

  • KERC had promised solar photovoltaic (PV) project developers that they would be exempted from wheeling charges for ten years after commissioning.
  • KERC had granted the concession of the tariff to the wind and mini-hydel projects.
  • It is not justifiable on the part of KERC to guarantee exemption and then to remove that guarantee. It is against the principles of promissory estoppel (a promise enforceable by law).
  • Such exemptions if withdrawn are not in public interest and can lead to project developers and investors suffering monetary loss leading to issues in serviceability of loans and would affect the economy.
  • KERC’s action boils down to discriminatory treatment.
  • KERC can only determine wheeling and banking charges prospectively not retrospectively.
  • Renewable energy project developers not to pay the increased charges.

Babu also added that the Karnataka High Court upheld the merits of the writ petitions filed. The Karnataka High Court upheld the fact that settled tariff contracts cannot be reopened unless by way of new regulations for the entire state.

According to the KERC order passed in 2014, just five percent of the transmission charges were levied as wheeling charges in the state of Karnataka. Now the concerned renewable energy developers need to pay the same for the ten years.

When contacted, a KERC official said that the Honorable Karnataka High Court’s order would be followed and refused to comment further.

RELATED POSTS

thumbnail
Top 5 States for Open Access Solar Installations in CY 2022

India added an impressive 2.5 GW open access solar capacity in 2022, registering a growth of 92% year-over-year (YoY), according to the 2022 Q4 & Annual Mercom India Solar Open Access Market Report. Karnataka emerged as the to...

March 23, 2023

Markets & Policy

Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules

The Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements betwe...

March 24, 2023

C&I

In Bengaluru, a 100 kW Solar System Can Save C&I Entities ₹1 Million Annually

Mercom India successfully concluded the C&I Clean Energy Meet 2023 in Bengaluru, where stakeholders in the solar sector and commercial and industrial entities converged to enthusiastically discuss the benefits of renewable ene...

March 24, 2023

Other

Gensol Acquires Solar Tracker Maker Scorpius for ₹1.35 Billion

Gensol Engineering, a part of solar engineering, procurement, and construction (EPC) company Gensol Group, has acquired India-based solar tracker manufacturer Scorpius Trackers for ₹1.35 billion ($16.4 million). Gensol said the ac...

March 23, 2023

Magazine

DON'T MISS AN ISSUE!

Mercom Cleantech Magazine

Get Your Copy Today!

magazines

Latest News

thumbnail
Intra-State Sections of Evacuation Infrastructure for Renewables Delayed

The Ministry of New and Renewable Energy (MNRE) told the Parliamentary Standing Committee on Energy that the intra-state stretches of the Green Energy Corridor (GEC) have been delayed due to various reasons, including...

March 24, 2023

thumbnail
EnBW Takes €2.4 Billion Final Investment Decision on Offshore Wind Project

German electric utility company Energie Baden-Wuerttemberg (EnBW) has made its final €2.4 billion (~$2.6 billion) investment decision on He Dreiht, a major wind project in the German North Sea. The project has a capacity of 960...

March 24, 2023

thumbnail
India Missed 2022 Renewables Target as Rooftop Solar and Wind fell Short

The Parliamentary Standing Committee on Energy report has isolated underwhelming progress on rooftop solar and wind energy projects as the primary reason for India falling short of achieving its renewable energy capacity target...

March 24, 2023

thumbnail
Researchers Aim to Accelerate Delivery of Space-Based Solar Power to Earth

Researchers at Northumbria University are studying ways of producing wireless electricity from space to Earth by harvesting the Sun’s energy. U.S.-based aerospace, defense, and information security organization Lockheed Martin...

March 24, 2023

thumbnail
Regulator Directs Wind Energy Firm, MSEDCL, to Recompute Delayed Payment Charge

The Maharashtra Electricity Regulatory Commission (MERC) recently directed Hindustan Petroleum Corporation (HPCL) and the Maharashtra State Electricity Distribution Company (MSEDCL) to recompute the delayed payment charge from...

March 24, 2023

thumbnail
One-Step Coating Could Make Perovskite Solar Cells Commercially Viable

The National Renewable Energy Laboratory (NREL) has devised a new way to produce perovskite solar cells that could speed its commercialization. Different layers are typically added sequentially to a conductive glass substrate to...

March 24, 2023

thumbnail
ACWA Power to Develop Solar and Energy Storage Projects in Uzbekistan

Saudi Arabia-based energy company ACWA Power has signed power purchase and investment agreements with  National Electric Grid of Uzbekistan, and the Ministry of Investment, Industry, and Trade to develop new solar and battery...

March 24, 2023

thumbnail
China Securities Regulatory Commission Approves Canadian Solar’s IPO

The China Securities Regulatory Commission has approved the registration of CSI Solar, the engineering, procurement, and construction arm of solar module maker Canadian Solar, to issue an initial public offering (IPO). The...

March 24, 2023

thumbnail
Renewables Accounted for 83% of the Total Generation Capacity Added in 2022

Renewable capacity grew by 9.6% in 2022, adding a record 295 GW worldwide. This accounts for 83% of all power capacity added last year and brings the global renewable generation capacity to 3,372 GW by the end of last year, a...

March 24, 2023

thumbnail
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules

The Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements...

March 24, 2023

MORE NEWS