Karnataka Commission Directs DISCOM to Compensate Solar Developer for GST Claims

The state regulator directed GESCOM to pay the compensation amount within 90 days

thumbnail

The Karnataka Electricity Regulatory Commission (KERC) ruled in favor of Parampujya Solar Energy, a solar power developer declaring that it is eligible for compensation due to the enactment of Goods and Services Tax (GST) per the ‘Change in Law’ clause.

The KERC ruling came as a relief to the solar developer, who in its petition claimed to have paid an increased cost for the project development and did not get compensated for it by Gulbarga Electricity Supply Company Limited (GESCOM) and Karnataka Renewable Energy Development Limited (KREDL)

Background 

KREDL had invited bids to develop 1,200 MW of solar power projects in Karnataka in November 2015.

Parampujya Solar Energy (a subsidiary of Adani Green Energy) submitted its proposal to develop a ground-mounted solar project in the Shorapur Taluk of Karnataka.

After evaluating, KREDL accepted the company’s bid to develop a 10 MW ground-mounted solar project and issued a letter of award on March 23, 2016.

The developer executed the power purchase agreement with GESCOM for setting the 10 MW solar project at a tariff of ₹5.35 (~$0.071)/kWh, which was also approved by the Commission.

The introduction of GST, thereafter, escalated the project’s capital cost making it unviable at the quoted tariff of ₹5.35 (~$0.071)/kWh. Due to GST implementation, the project’s cost increased by ₹8.09 million (~$107,675).

The developer sent a notice to GESCOM regarding the ‘Change in Law’ event. However, GESCOM did not respond.

The developer, in its petition, informed the Commission that the GST introduction made a significant impact on the actual cost of the solar project and should be approved as a ‘Change in Law’ event in terms of the PPA.

GESCOM’s response

 GESCOM said the company executed a PPA with the solar developer in May 2016 and the Commission approved the PPA in October 2016.

The solar developer was required to commission the project within 12 months from the approval date and was also required to achieve conditions precedent within eight months – on or before June 5, 2017.

The Government of India introduced the GST on April 12, 2017. Karnataka GST was enacted on June 27, 2017. The Central Goods and Services Tax Act of 2017 and the Integrated Goods and Services Tax Act of 2017 were enacted on July 1, 2017, for levy and collection of tax on inter-state supply of goods or services or both.

GESCOM said the solar developer executed PPA and started implementing the project much before the implementation of GST. Therefore, the enactment of GST did not affect the developer and was not entitled to relief.

Commission’s analysis

After analyzing submissions made by both parties, the Commission observed that the ‘Change in Law’ affects adoption, promulgation, amendment, modification, or repeal of any law in India as per the PPA.

The Commission also noted the solar developer sent a notice to GESCOM stating that GST implementation should be a ‘Change in Law’ event as it is not factored in the PPA.

Therefore, the state regulator opined that the change in duties consequent upon the GST laws result in the change in the cost of inputs required for power generation by the company, and the same is to be considered as ‘Change in Law.’

The Commission directed GESCOM and KREDL to compensate the developer for the claims in three equal installments within 90 days as per the calculations below:

GST Compensation To be Paid by GESCOM to Solar Developer

However, the Commission noted that no specific provision is provided in the PPA to restore the economic position of the solar developer as it was before the introduction of GST laws on account of a ‘Change in Law’ event. Therefore, the question of allowing carrying costs does not arise.

Last month, KERC ruled in favor of a solar developer and allowed compensation for four solar projects of 20 MW each on the grounds of the imposition of GST.

Subscribe to Mercom’s real-time Regulatory Updates to ensure you do not miss any critical updates from the renewable industry.

RELATED POSTS

thumbnail
Top 5 States for Open Access Solar Installations in CY 2022

India added an impressive 2.5 GW open access solar capacity in 2022, registering a growth of 92% year-over-year (YoY), according to the 2022 Q4 & Annual Mercom India Solar Open Access Market Report. Karnataka emerged as the to...

March 23, 2023

Markets & Policy

Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules

The Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements betwe...

March 24, 2023

C&I

In Bengaluru, a 100 kW Solar System Can Save C&I Entities ₹1 Million Annually

Mercom India successfully concluded the C&I Clean Energy Meet 2023 in Bengaluru, where stakeholders in the solar sector and commercial and industrial entities converged to enthusiastically discuss the benefits of renewable ene...

March 24, 2023

Other

Gensol Acquires Solar Tracker Maker Scorpius for ₹1.35 Billion

Gensol Engineering, a part of solar engineering, procurement, and construction (EPC) company Gensol Group, has acquired India-based solar tracker manufacturer Scorpius Trackers for ₹1.35 billion ($16.4 million). Gensol said the ac...

March 23, 2023

Magazine

DON'T MISS AN ISSUE!

Mercom Cleantech Magazine

Get Your Copy Today!

magazines

Latest News

thumbnail
Intra-State Sections of Evacuation Infrastructure for Renewables Delayed

The Ministry of New and Renewable Energy (MNRE) told the Parliamentary Standing Committee on Energy that the intra-state stretches of the Green Energy Corridor (GEC) have been delayed due to various reasons, including...

March 24, 2023

thumbnail
EnBW Takes €2.4 Billion Final Investment Decision on Offshore Wind Project

German electric utility company Energie Baden-Wuerttemberg (EnBW) has made its final €2.4 billion (~$2.6 billion) investment decision on He Dreiht, a major wind project in the German North Sea. The project has a capacity of 960...

March 24, 2023

thumbnail
India Missed 2022 Renewables Target as Rooftop Solar and Wind fell Short

The Parliamentary Standing Committee on Energy report has isolated underwhelming progress on rooftop solar and wind energy projects as the primary reason for India falling short of achieving its renewable energy capacity target...

March 24, 2023

thumbnail
Researchers Aim to Accelerate Delivery of Space-Based Solar Power to Earth

Researchers at Northumbria University are studying ways of producing wireless electricity from space to Earth by harvesting the Sun’s energy. U.S.-based aerospace, defense, and information security organization Lockheed Martin...

March 24, 2023

thumbnail
Regulator Directs Wind Energy Firm, MSEDCL, to Recompute Delayed Payment Charge

The Maharashtra Electricity Regulatory Commission (MERC) recently directed Hindustan Petroleum Corporation (HPCL) and the Maharashtra State Electricity Distribution Company (MSEDCL) to recompute the delayed payment charge from...

March 24, 2023

thumbnail
One-Step Coating Could Make Perovskite Solar Cells Commercially Viable

The National Renewable Energy Laboratory (NREL) has devised a new way to produce perovskite solar cells that could speed its commercialization. Different layers are typically added sequentially to a conductive glass substrate to...

March 24, 2023

thumbnail
ACWA Power to Develop Solar and Energy Storage Projects in Uzbekistan

Saudi Arabia-based energy company ACWA Power has signed power purchase and investment agreements with  National Electric Grid of Uzbekistan, and the Ministry of Investment, Industry, and Trade to develop new solar and battery...

March 24, 2023

thumbnail
China Securities Regulatory Commission Approves Canadian Solar’s IPO

The China Securities Regulatory Commission has approved the registration of CSI Solar, the engineering, procurement, and construction arm of solar module maker Canadian Solar, to issue an initial public offering (IPO). The...

March 24, 2023

thumbnail
Renewables Accounted for 83% of the Total Generation Capacity Added in 2022

Renewable capacity grew by 9.6% in 2022, adding a record 295 GW worldwide. This accounts for 83% of all power capacity added last year and brings the global renewable generation capacity to 3,372 GW by the end of last year, a...

March 24, 2023

thumbnail
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules

The Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements...

March 24, 2023

MORE NEWS