Gujarat Regulator Rejects Deadline Extensions for 16 MW Solar Projects
The Commission noted that the petitioners failed to substantiate their force majeure claims
November 20, 2026
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Gujarat Electricity Regulatory Commission (GERC) has rejected petitions from four ceramic tile manufacturers seeking extension of the scheduled commissioning dates (SCOD) for power evacuation infrastructure linked to their captive solar projects totaling 16 MW.