Discount Rate of Annuity Payments to Solar Developers Will be 10.41%: CERC
Solar power developers to pay taxes on monthly annuity payments as per PPA terms
August 24, 2021
The Central Electricity Regulatory Commission (CERC), in a recent order, has reiterated Solar Energy Corporation of India’s (SECI) proposal for a 10.41% discount rate on annuity payments towards the additional expenses incurred by solar power developers on account of ‘Change in Law’ events.
It, however, rejected the request of solar power developers that interest on customs bonds should be covered under the Change in Law and paid in a lump sum. The Commission directed solar power developers to pay all statutory taxes, duties, levies, and cess on monthly annuity payments as per the terms of power purchase agreements (PPAs).
Background
SECI had requested the Commission to direct distribution companies (DISCOMs) to pay the amount evaluated as the impact of ‘Change in Law’ on account of Goods and Services Tax (GST) and Safeguard Duty on an annuity basis. SECI requested CERC to direct DISCOMs to comply with the order and release the amount towards the evaluated claims of solar power developers on account of GST and safeguard duty.
SECI noted that the Commission had decided that the introduction of GST laws and imposition of safeguard duty were ‘Change in Law’ events as per the terms of various PPAs and power sale agreements (PSAs).
In an earlier order, the Commission ruled that GST claims must be paid within 60 days from its order (February 2019) or from the date of submission of claims by solar power developers, whichever is later. If SECI or DISCOMs failed to pay, it would attract late payment surcharges as per PPA terms.
Thereafter, the Ministry of New and Renewable Energy (MNRE) directed the central agencies to proceed with payments against the ‘Change in Law’ claims as per the annuity model.
To design the methodology for monthly (annuity) payments, SECI considered a discounting factor of 10.41%, an interest rate for loan component of the capital cost as provided in the renewable energy tariff order dated March 19, 2019. The period of payment of compensation on account of GST and Safeguard Duty was set at 13 years from the commercial operation date (COD).
Regarding the discounting factor, solar power developers said that SECI reevaluated and calculated the monthly annuity payment, with the proposed annuity rate of 10.41% for the entire 100% of additional CAPEX (capital expenditure) incurred by solar power developers on account of ‘Change in Law’ event. However, the rate of 10.41% was applicable only for the debt part (70%) of the additional CAPEX and cannot apply to the remaining 30% equity portion.
Solar power developers argued that SECI’s method of arriving at annuity payments was incorrect and not in line with the CERC’s Renewable Energy Tariff Regulations.
After examining documents submitted by solar power developers, SECI evaluated solar power developers’ claims regarding GST and safeguard duty and notified solar power developers and DISCOMs purchasing the power. However, only Rajasthan DISCOMs released some amount towards GST claims of ACME Jodhpur Solar Power, ACME Rewa Solar Energy, and Phelan India RJ. Despite the efforts of SECI, other DISCOMs did not make payments to settle the claims as per the provisions of PPAs and PSAs.
SECI said DISCOMs had to pay ₹1.04 billion (~$14.13 million) as compensation on account of GST claims. Of this, SECI would pay ₹803.11 million (~$10.82 million) to solar power developers. The outstanding amount of ₹562.38 million (~$7.58 million) was due from DISCOMs as of April 20, 2021.
As compensation for safeguard duty imposition, DISCOMs had to pay ₹8.15 billion (~$110 million) to SECI. In turn, SECI had to pay ₹803.11 million to solar power developers on an annuity basis. DISCOMs had only paid ₹274.36 million (~$3.69 million) to SECI.
In the light of the pending payments from DISCOMs, SECI proposed to pay compensation to solar power developers on an annuity basis through the payment security fund.
Commission’s analysis
The Commission observed that SECI had proposed the annuity payment with a discounting factor of 10.41%. Solar power developers stated that the discounting factor should be 12.90% annually by factoring in the interest on loans at 10.41% and the return on equity of 14% and applying a debt-equity ratio of 70:30 as per Renewable Energy Tariff Regulations. Some solar developers said that the discounting factor should be 13.14% annually or higher.
On the other hand, DISCOMs proposed a discounting factor of 9.36% as per the Commission’s Renewable Energy Tariff order dated March 19, 2019.
In its analysis, the Commission stated that SECI and solar power developers are in consensus regarding interest rates on loans. The individual tariff components such as capital cost and expected return on equity are ‘unknown’ as the tariff is determined through a competitive bidding process.
Therefore, the Commission said that it would not consider the contentions of solar power developers for a discounting factor of 12.90% or 13.14% and of the DICSCOMs for a discounting factor of 9.36%.
The Commission stated that the annuity rate should be 10.41% towards the expenditure incurred by solar power developers on account of the ‘Change in Law’ events. In addition, SECI or DISCOMs must pay a late payment surcharge for the delayed period as per respective PPAs or PSAs, if they failed to pay monthly annuity payments on time.
The Commission also directed solar power developers to pay all statutory taxes, duties, levies, and cess on monthly annuity payments as per the terms of PPAs.
Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.
Get the most relevant India solar and clean energy news.
RECENT POSTS
LATEST HEADLINES
Intra-State Sections of Evacuation Infrastructure for Renewables Delayed
Mar 24, 2023
EnBW Takes €2.4 Billion Final Investment Decision on Offshore Wind Project
Mar 24, 2023
India Missed 2022 Renewables Target as Rooftop Solar and Wind fell Short
Mar 24, 2023
Researchers Aim to Accelerate Delivery of Space-Based Solar Power to Earth
Mar 24, 2023
Regulator Directs Wind Energy Firm, MSEDCL, to Recompute Delayed Payment Charge
Mar 24, 2023
India added an impressive 2.5 GW open access solar capacity in 2022, registering a growth of 92% year-over-year (YoY), according to the 2022 Q4 & Annual Mercom India Solar Open Access Market Report. Karnataka emerged as the to...
March 23, 2023
Markets & Policy
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar ModulesThe Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements betwe...
March 24, 2023
C&I
In Bengaluru, a 100 kW Solar System Can Save C&I Entities ₹1 Million AnnuallyMercom India successfully concluded the C&I Clean Energy Meet 2023 in Bengaluru, where stakeholders in the solar sector and commercial and industrial entities converged to enthusiastically discuss the benefits of renewable ene...
March 24, 2023
Other
Gensol Acquires Solar Tracker Maker Scorpius for ₹1.35 BillionGensol Engineering, a part of solar engineering, procurement, and construction (EPC) company Gensol Group, has acquired India-based solar tracker manufacturer Scorpius Trackers for ₹1.35 billion ($16.4 million). Gensol said the ac...
March 23, 2023
Trending News
Technology
Researchers Find Solution to Manage Load in Solar PV & Storage Systems
February 28, 2023
February 27, 2023
February 24, 2023
January 17, 2023
Magazine
Latest News
The Ministry of New and Renewable Energy (MNRE) told the Parliamentary Standing Committee on Energy that the intra-state stretches of the Green Energy Corridor (GEC) have been delayed due to various reasons, including...
March 24, 2023
German electric utility company Energie Baden-Wuerttemberg (EnBW) has made its final €2.4 billion (~$2.6 billion) investment decision on He Dreiht, a major wind project in the German North Sea. The project has a capacity of 960...
March 24, 2023
The Parliamentary Standing Committee on Energy report has isolated underwhelming progress on rooftop solar and wind energy projects as the primary reason for India falling short of achieving its renewable energy capacity target...
March 24, 2023
Researchers at Northumbria University are studying ways of producing wireless electricity from space to Earth by harvesting the Sun’s energy. U.S.-based aerospace, defense, and information security organization Lockheed Martin...
March 24, 2023
The Maharashtra Electricity Regulatory Commission (MERC) recently directed Hindustan Petroleum Corporation (HPCL) and the Maharashtra State Electricity Distribution Company (MSEDCL) to recompute the delayed payment charge from...
March 24, 2023
The National Renewable Energy Laboratory (NREL) has devised a new way to produce perovskite solar cells that could speed its commercialization. Different layers are typically added sequentially to a conductive glass substrate to...
March 24, 2023
Saudi Arabia-based energy company ACWA Power has signed power purchase and investment agreements with National Electric Grid of Uzbekistan, and the Ministry of Investment, Industry, and Trade to develop new solar and battery...
March 24, 2023
The China Securities Regulatory Commission has approved the registration of CSI Solar, the engineering, procurement, and construction arm of solar module maker Canadian Solar, to issue an initial public offering (IPO). The...
March 24, 2023
Renewable capacity grew by 9.6% in 2022, adding a record 295 GW worldwide. This accounts for 83% of all power capacity added last year and brings the global renewable generation capacity to 3,372 GW by the end of last year, a...
March 24, 2023
The Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements...
March 24, 2023
Get the most relevant India solar and clean energy news.
POPULAR POSTS
Intra-State Sections of Evacuation Infrastructure for Renewables Delayed
Mar 24, 2023
EnBW Takes €2.4 Billion Final Investment Decision on Offshore Wind Project
Mar 24, 2023
India Missed 2022 Renewables Target as Rooftop Solar and Wind fell Short
Mar 24, 2023
Researchers Aim to Accelerate Delivery of Space-Based Solar Power to Earth
Mar 24, 2023
Regulator Directs Wind Energy Firm, MSEDCL, to Recompute Delayed Payment Charge
Mar 24, 2023
One-Step Coating Could Make Perovskite Solar Cells Commercially Viable
Mar 24, 2023
ACWA Power to Develop Solar and Energy Storage Projects in Uzbekistan
Mar 24, 2023