Deviations to the Bidding Guidelines for Omkareshwar Floating Solar Project Approved
The Commission said the approval of PPA and PSA was required as per the regulations
October 7, 2022
The Madhya Pradesh Electricity Regulatory Commission (MPERC) recently approved deviations to the bidding guidelines for developing the Omkareshwar floating solar power project (Phase II).
The Commission noted that the approval of the power purchase agreement (PPA) and power sale agreement (PSA) would be necessary per the provisions of the Electricity Act 2003 and applicable MPERC regulations.
Rewa Ultra Mega Solar (RUMSL) and Madhya Pradesh Power Management Company (MPPMCL) had jointly filed a petition for approval of certain deviations from the bidding guidelines issued by the Ministry of Power for the development of the 600 MW floating solar project.
Background
Given the project-specific requirements, the petitioners had sought approval of deviations concerning:
- Notification of force majeure event
- Offtake constraints due to lack of readiness of power evacuation infrastructure
- Default by solar project developer and consequences
- Default on account of the developer’s failure to supply energy as per PPA
- Inclusion of epidemic, pandemic, quarantine, lockdown, or similar actions ordered by any government authority as ‘force majeure events
- Termination due to a non-natural force Majure event
- Commissioning timelines
- Event of the reservoir’s minimum water level going below 190.5 meters
In July this year, RUMSL invited bids to develop 300 MW of floating solar projects (3×100 MW, Phase-II) at the Omkareshwar reservoir.
Commission’s analysis –
Notification of a force majeure event
The Commission observed that the petitioners had submitted that the affected party should be provided with a maximum period of 15 days in place of seven days to notify the other party of the occurrence of a force majeure event. The Commission approved this deviation.
Offtake constraints
Regarding the offtake constraints due to the lack of evacuation infrastructure, the Commission noted that the intent of the proposed changes in connection with generation compensation due to transmission infrastructure constraints was to provide greater certainty to investors. This deviation was allowed.
Default by solar project developer
Regarding defaults by developers, the Commission said that the petitioners had submitted that if the developers default and fail to cure it within the prescribed period, procurers will have the right to terminate the PPAs. Under such conditions, the developers would be liable to pay damages to the procurer.
The Commission observed that the deviations sought in respect of termination consequences were an attempt at further detailing the consequences of default. The deviation sought in this regard was approved.
Failure to supply energy as per PPA
The Commission noted that the petitioners had proposed to incorporate a provision that if the developers failed to supply energy up to their yearly minimum supply obligation, they would be liable for payment of damages.
It said that the intent of the proposed changes in connection with the termination consequences was to give the parties an option to avoid termination of the PPAs and continue with the project, which may be economically beneficial to the stakeholders. The Commission acknowledged the intent and considered the deviation sought in this regard.
Force majeure events
The petitioners submitted that the definition of force majeure under the solar bidding guidelines does not specifically include any widespread occurrence of a disease affecting the construction and operation of the solar project.
The Commission observed that the Covid-19 outbreak led to a lockdown in the entire industry, affecting the entire activities. However, the Commission stated that the expression ‘pandemic’ or ‘epidemic’ without a qualification defining the inability of the project developer to execute the project would be too open and needed to be restricted to ‘pandemic resulting in lockdown or similar action ordered by any government authority.’ Accordingly, this deviation was allowed with a limited scope to mean ‘pandemic resulting in lockdown or similar action ordered by any government authority.’
Non-natural force majeure event
The petitioners had proposed that in the case of a non-natural force majeure event, developers should be allowed to terminate the project agreements after 365 days from the issuance of the notice instead of 180 days, as per the solar bidding guidelines. The proposal was allowed.
Commissioning timelines
The petitioners submitted that during the stakeholder interaction with the prospective bidders for Phase II, it was decided that a longer commissioning timeframe of 21 months would allow the bidders to manage the shortage of modules and floats required for project construction and commissioning.
The Commission granted the extension since it would help enhance the project’s bankability and reduce the bid tariff.
Reservoir’s minimum water level This clause was added to ensure the uninterrupted operation of the floating solar project by maintaining the minimum water level of 190.50 meters in the Omkareshwar reservoir.
The Commission observed that the above provision was specific to the Omkareshwar floating solar project and was not a deviation from the bidding guidelines. It said that the proposed amendment was appropriate to mitigate the risk of the generation below the level of 190.50 meters.
Earlier this year, Amp Energy, NHDC, and SJVN were declared winners in RUMSL’s auction for the 600 MW floating solar park3.
Subscribe to our real-time Regulatory Updates to ensure that you never miss any critical updates from the renewable energy industry.
Get the most relevant India solar and clean energy news.
RECENT POSTS
LATEST HEADLINES
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules
Mar 24, 2023
Intra-State Sections of Evacuation Infrastructure for Renewables Delayed
Mar 24, 2023
EnBW Takes €2.4 Billion Final Investment Decision on Offshore Wind Project
Mar 24, 2023
India Missed 2022 Renewables Target as Rooftop Solar and Wind fell Short
Mar 24, 2023
Researchers Aim to Accelerate Delivery of Space-Based Solar Power to Earth
Mar 24, 2023
India added an impressive 2.5 GW open access solar capacity in 2022, registering a growth of 92% year-over-year (YoY), according to the 2022 Q4 & Annual Mercom India Solar Open Access Market Report. Karnataka emerged as the to...
March 23, 2023
Markets & Policy
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar ModulesThe Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements betwe...
March 24, 2023
C&I
In Bengaluru, a 100 kW Solar System Can Save C&I Entities ₹1 Million AnnuallyMercom India successfully concluded the C&I Clean Energy Meet 2023 in Bengaluru, where stakeholders in the solar sector and commercial and industrial entities converged to enthusiastically discuss the benefits of renewable ene...
March 24, 2023
Other
Gensol Acquires Solar Tracker Maker Scorpius for ₹1.35 BillionGensol Engineering, a part of solar engineering, procurement, and construction (EPC) company Gensol Group, has acquired India-based solar tracker manufacturer Scorpius Trackers for ₹1.35 billion ($16.4 million). Gensol said the ac...
March 23, 2023
Trending News
Mercom Focus
Researchers Find Solution to Manage Load in Solar PV & Storage Systems
February 28, 2023
February 27, 2023
February 24, 2023
January 17, 2023
Magazine
Latest News
The Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements...
March 24, 2023
The Ministry of New and Renewable Energy (MNRE) told the Parliamentary Standing Committee on Energy that the intra-state stretches of the Green Energy Corridor (GEC) have been delayed due to various reasons, including...
March 24, 2023
German electric utility company Energie Baden-Wuerttemberg (EnBW) has made its final €2.4 billion (~$2.6 billion) investment decision on He Dreiht, a major wind project in the German North Sea. The project has a capacity of 960...
March 24, 2023
The Parliamentary Standing Committee on Energy report has isolated underwhelming progress on rooftop solar and wind energy projects as the primary reason for India falling short of achieving its renewable energy capacity target...
March 24, 2023
Researchers at Northumbria University are studying ways of producing wireless electricity from space to Earth by harvesting the Sun’s energy. U.S.-based aerospace, defense, and information security organization Lockheed Martin...
March 24, 2023
The Maharashtra Electricity Regulatory Commission (MERC) recently directed Hindustan Petroleum Corporation (HPCL) and the Maharashtra State Electricity Distribution Company (MSEDCL) to recompute the delayed payment charge from...
March 24, 2023
The National Renewable Energy Laboratory (NREL) has devised a new way to produce perovskite solar cells that could speed its commercialization. Different layers are typically added sequentially to a conductive glass substrate to...
March 24, 2023
Saudi Arabia-based energy company ACWA Power has signed power purchase and investment agreements with National Electric Grid of Uzbekistan, and the Ministry of Investment, Industry, and Trade to develop new solar and battery...
March 24, 2023
The China Securities Regulatory Commission has approved the registration of CSI Solar, the engineering, procurement, and construction arm of solar module maker Canadian Solar, to issue an initial public offering (IPO). The...
March 24, 2023
Renewable capacity grew by 9.6% in 2022, adding a record 295 GW worldwide. This accounts for 83% of all power capacity added last year and brings the global renewable generation capacity to 3,372 GW by the end of last year, a...
March 24, 2023
Get the most relevant India solar and clean energy news.
POPULAR POSTS
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules
Mar 24, 2023
Intra-State Sections of Evacuation Infrastructure for Renewables Delayed
Mar 24, 2023
EnBW Takes €2.4 Billion Final Investment Decision on Offshore Wind Project
Mar 24, 2023
India Missed 2022 Renewables Target as Rooftop Solar and Wind fell Short
Mar 24, 2023
Researchers Aim to Accelerate Delivery of Space-Based Solar Power to Earth
Mar 24, 2023