CERC Upholds Solar Developer’s Compensation Claims Under Change in Law Due to GST
MPPMCL and DMRC were directed to pay the dues along with late payment surcharge
December 9, 2022
Ruling in favor of a solar developer, the Central Electricity Regulatory Commission (CERC) directed the Madhya Pradesh Power Management Company (MPPMCL) and Delhi Metro Rail Corporation (DMRC) to settle the balance goods and service tax (GST) claims along with the payment of late payment surcharge.
Background
In March 2013, Rewa Ultra Mega Solar (RUMSL) invited bids to develop 750 MW of solar projects split into three units of 250 MW each.
ACME Solar Holdings was selected as the successful bidder to develop one of the units.
In 2017, ACME Solar incorporated a special purpose vehicle, ACME Jaipur Solar Power, to execute the project.
Later, ACME Solar entered into two separate power purchase agreements (PPAs) with MPPMCL and DMRC.
On July 1, 2017, the GST laws were introduced, which subsumed multiple extant indirect taxes. ACME filed a petition seeking compensation due to additional costs incurred on account of GST.
The Commission had allowed the petition, and ACME submitted a GST claim of ₹514.8 million (~$6.26 million).
MPPMCL paid ₹297.16 million (~$3.61 million) against a claim of ₹401.5 million (~$4.88 million), while DMRC paid ₹80.83 million (~$982,114) against a claim amount of ₹113.3 million (~$1.38 million).
ACME submitted that GST claims for ₹121.96 million (~$1.48 million) against the invoices for which one-to-one correlation with GST returns could not be established were disallowed for payment by the respondents.
Further, MPPMCL wrongly considered tax in the pre-GST regime as ₹157.14 million (~$1.91 million). However, as per the statutory auditor certificate, the tax in the pre-GST regime is ₹143.33 million (~$1.74 million). Therefore, an additional deduction of ₹13.77 million (~$167,325) has been wrongfully made by MPPMCL and is thus required for the balance payment.
ACME contended that MPPMCL and DMRC were liable to pay GST claims against the invoices submitted when they were not registered under GST but paid to its vendors anyway.
ACME said it should be compensated by considering a pre-GST tax rate of 11% on the 40% value of services and a 15% tax rate on the balance 60% of the value of services which increased to 18% post-GST. It also sought that it be compensated for the balance GST claims along with late payment surcharge (LPS) as applicable under the PPA.
MPPMCL and DMRC refuted the claims because ACME failed to establish one-to-one co-relation for its claims without GST returns.
ACME argued that change in law rules have no application where the other party to the agreement has already disputed or contested it.
Commission’s analysis
The Commission directed MPPMCL and DMRC to reconcile and process those invoices for compensation on which ACME had paid GST to its registered vendors, and the vendors have deposited the GST with the Government.
The central regulator observed that ACME claimed the tax was payable at a 13.40% −weighted average of 11% on 40% and 15% of the remaining 60% − in the pre-GST regime. However, MPPMCL and DMRC considered a flat 15% tax rate for the entire value of services.
The Commission stated that the parties should reconcile and process the invoices considering the actual tax paid in the GST period and the tax payable in the pre-GST period.
It also directed MPPMCL and DMRC to process the due claims against the invoices already raised along with the LPS as provided under the PPA.
Earlier, CERC ruled in favor of ACME Jaipur and asked MPPMCL and DMRC to settle the safeguard duty claims along with the payment of the late payment surcharge within 30 days.
Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.
Get the most relevant India solar and clean energy news.
RECENT POSTS
LATEST HEADLINES
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules
Mar 24, 2023
Intra-State Sections of Evacuation Infrastructure for Renewables Delayed
Mar 24, 2023
EnBW Takes €2.4 Billion Final Investment Decision on Offshore Wind Project
Mar 24, 2023
India Missed 2022 Renewables Target as Rooftop Solar and Wind fell Short
Mar 24, 2023
Researchers Aim to Accelerate Delivery of Space-Based Solar Power to Earth
Mar 24, 2023
India added an impressive 2.5 GW open access solar capacity in 2022, registering a growth of 92% year-over-year (YoY), according to the 2022 Q4 & Annual Mercom India Solar Open Access Market Report. Karnataka emerged as the to...
March 23, 2023
Markets & Policy
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar ModulesThe Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements betwe...
March 24, 2023
C&I
In Bengaluru, a 100 kW Solar System Can Save C&I Entities ₹1 Million AnnuallyMercom India successfully concluded the C&I Clean Energy Meet 2023 in Bengaluru, where stakeholders in the solar sector and commercial and industrial entities converged to enthusiastically discuss the benefits of renewable ene...
March 24, 2023
Other
Gensol Acquires Solar Tracker Maker Scorpius for ₹1.35 BillionGensol Engineering, a part of solar engineering, procurement, and construction (EPC) company Gensol Group, has acquired India-based solar tracker manufacturer Scorpius Trackers for ₹1.35 billion ($16.4 million). Gensol said the ac...
March 23, 2023
Trending News
Mercom Focus
Researchers Find Solution to Manage Load in Solar PV & Storage Systems
February 28, 2023
February 27, 2023
February 24, 2023
January 17, 2023
Magazine
Latest News
The Ministry of New and Renewable Energy (MNRE) has modified the Approved List of Models and Manufacturers (ALMM) guidelines and provided exceptions to broaden the qualification criteria for modules produced under agreements...
March 24, 2023
The Ministry of New and Renewable Energy (MNRE) told the Parliamentary Standing Committee on Energy that the intra-state stretches of the Green Energy Corridor (GEC) have been delayed due to various reasons, including...
March 24, 2023
German electric utility company Energie Baden-Wuerttemberg (EnBW) has made its final €2.4 billion (~$2.6 billion) investment decision on He Dreiht, a major wind project in the German North Sea. The project has a capacity of 960...
March 24, 2023
The Parliamentary Standing Committee on Energy report has isolated underwhelming progress on rooftop solar and wind energy projects as the primary reason for India falling short of achieving its renewable energy capacity target...
March 24, 2023
Researchers at Northumbria University are studying ways of producing wireless electricity from space to Earth by harvesting the Sun’s energy. U.S.-based aerospace, defense, and information security organization Lockheed Martin...
March 24, 2023
The Maharashtra Electricity Regulatory Commission (MERC) recently directed Hindustan Petroleum Corporation (HPCL) and the Maharashtra State Electricity Distribution Company (MSEDCL) to recompute the delayed payment charge from...
March 24, 2023
The National Renewable Energy Laboratory (NREL) has devised a new way to produce perovskite solar cells that could speed its commercialization. Different layers are typically added sequentially to a conductive glass substrate to...
March 24, 2023
Saudi Arabia-based energy company ACWA Power has signed power purchase and investment agreements with National Electric Grid of Uzbekistan, and the Ministry of Investment, Industry, and Trade to develop new solar and battery...
March 24, 2023
The China Securities Regulatory Commission has approved the registration of CSI Solar, the engineering, procurement, and construction arm of solar module maker Canadian Solar, to issue an initial public offering (IPO). The...
March 24, 2023
Renewable capacity grew by 9.6% in 2022, adding a record 295 GW worldwide. This accounts for 83% of all power capacity added last year and brings the global renewable generation capacity to 3,372 GW by the end of last year, a...
March 24, 2023
Get the most relevant India solar and clean energy news.
POPULAR POSTS
Government Clarifies ALMM Enlistment Guidelines for Co-branded Solar Modules
Mar 24, 2023
Intra-State Sections of Evacuation Infrastructure for Renewables Delayed
Mar 24, 2023
EnBW Takes €2.4 Billion Final Investment Decision on Offshore Wind Project
Mar 24, 2023
India Missed 2022 Renewables Target as Rooftop Solar and Wind fell Short
Mar 24, 2023
Researchers Aim to Accelerate Delivery of Space-Based Solar Power to Earth
Mar 24, 2023